Change order script · New feature

Client requests a feature after launch

The project launched last week and the warranty covers defects. The client sends a feature request labelled as a bug. Here is how to separate the two kindly.

# ngo-shop-clientNorthgate Outfitters
BA

Ben Adeyemi10:42 AM

Found a bug: customers can't save items to a wishlist. Can you fix that under warranty?

Possible scope change, visible to your team only

Cites SOW section 9.1, Warranty. Estimated 26 hours. Change order draft ready for PM review.

The situation

Warranty periods cover defects: things that do not work as specified. A wishlist was never in scope, so its absence is not a defect. The client may genuinely believe it is a bug. Handling this well matters because post-launch is when the relationship either becomes a retainer or ends.

Why this script works

The script thanks the client, checks the spec openly, and explains the difference between a defect and a feature in friendly terms. It then makes the feature easy to buy and suggests a backlog for future work, which opens the door to ongoing engagement.

Scenario
New feature
Clause to cite
SOW section 9.1, Warranty
Typical effort
26 hours
Typical change order
$4,290 at $165/hr
Reply within
Same business day

The script

Three versions: the quick reply, the email and the nudge.

Start in the channel where the request arrived, then follow with the email and change order. Copy any version and replace the bracketed placeholders.

PM

Youdraft, reply in thread

Hi [Name], thanks for flagging! I checked the spec: wishlists weren't part of the original build (Appendix A), so this is a new feature rather than a bug, and the warranty covers fixes to built features. The good news is it's a great idea, and we can scope it quickly. I'll send an estimate, and if you have a few more ideas, we could bundle them into a small post-launch phase.

Replace every [bracketed] placeholder before sending. Your PM approves every message, TWINJAM never contacts clients on its own.

What not to say

Small wording changes decide whether the client hears help or a bill.

Avoid Say insteadWhy
“That's not a bug.”“Wishlists weren't in the original build, so this is a new feature.”Explains the classification without contradicting them.
“Warranty doesn't cover that.”“Warranty covers fixes to built features, here is the estimate for this one.”Pairs the boundary with a next step.
“Sure, small fix.”“Here is a quick estimate.”Post-launch freebies quickly become a support desk.

SOW clause to cite

SOW section 9.1, Warranty

For 30 days after launch, Agency will fix defects where delivered features do not function as specified in Appendix A. New features and enhancements are outside the warranty and handled under the Change Control clause.

No clause like this in your SOW? Use one of the SOW templates for your next engagement, and have your counsel review final contract language.

CO-NGO-SHOP-07

Client requests a feature after launch

Awaiting client approval
Line itemHoursAmount
Wishlist data model and APIEngineer8$1,320
Save, view and share UI on product and account pagesFront-end engineer10$1,650
Guest to logged-in wishlist syncEngineer4$660
Testing and releaseQA engineer4$660
Total26$4,290

Priced at a $165 blended hourly rate. Cites SOW section 9.1, Warranty.

Step by step

From the client’s message to a signed change order.

The script is one step. The process around it is what keeps scope conversations short and friendly.

  1. 1

    Check the request against your signed SOW. For this scenario the clause to cite is usually SOW section 9.1, Warranty.

  2. 2

    Reply the same day in the channel where the request arrived, using the Slack version. Agree with the goal before you mention scope.

  3. 3

    Estimate the work as line items with hours. This scenario typically lands around 26 hours.

  4. 4

    Send the email version with the change order attached and two or three options, including a lighter or free path where one exists.

  5. 5

    Set a decision date tied to the schedule. If there is no reply in three business days, send the follow-up.

  6. 6

    Record the approval or the decision to defer, so the SOW baseline stays accurate for the next request.

Agency Change Order Scriptbook

12 polite Slack and email templates to ask for more budget without friction.

The scriptbook collects the twelve conversations agency PMs dread most, from the fourth design round to the after-launch feature, with the SOW clause to cite and a change order form for each.

Spot the request before the work starts.

TWINJAM flags out-of-scope requests in Slack, Teams and Jira, cites the SOW clause and drafts a change order like this one for your PM to approve.